SSE plans to decommission Yorkshire gas storage site without government support

The company says Atwick could begin rewatering in summer 2027 because current market conditions do not support continued commercial operation. Ministers have not announced a decision on possible support.

SSE says it expects to begin rewatering its Atwick gas storage site in East Yorkshire in summer 2027 unless government policy changes, starting a multi-year process that would lead to decommissioning. The company says current market arrangements and weak trading spreads do not support the site’s continued commercial operation.

The timetable is conditional, and the company has not announced an immediate closure date. Its interim-results material says rewatering would be followed by decommissioning over time if there is no policy intervention.

Government has not committed to support

In a letter to Parliament dated 27 October, Energy Secretary Miatta Fahnbulleh said the government was exploring whether revenue support for gas infrastructure, including storage, might be needed. She said further analysis was required and that a fuller response would follow. The letter did not announce a support decision or commitment.

SSE’s position follows concerns about the commercial case for operating Atwick under current market conditions. The company’s stated rationale is that adverse market dynamics and a lack of favourable price spreads undermine the site’s viability.

Site capacity and wider system context

Atwick is near Hornsea in East Yorkshire. SSE’s statement describes it as an eight-cavern facility with capacity of about 309 million cubic metres. The government’s 2026 National Risk Assessment lists the Hornsea site, owned by SSE Hornsea Limited, at 311 million cubic metres.

The assessment describes gas storage as a flexibility resource that can supplement other supply, particularly during short-term changes in supply or demand. It lists eight UK storage sites and says the system met the infrastructure standard for winter 2026/27, with an N-1 result of 103.6%. That context does not establish that the proposed decommissioning would cause an immediate supply crisis.

The government assessment and SSE’s announcement frame the issue differently: the first describes storage’s role in system flexibility, while SSE says current commercial conditions do not justify keeping Atwick operating without a policy change. The available material establishes no final government decision on support.